Proposal CFHWY00300 |
Date Generated: | 04/08/2022 | Sections: | 1 |
Date Revised: | 05/05/2022 | Amendments: | 3 |
Call Order: | 1 | Highway Number: | |
Items: | 66 | Counties: | Kenai Peninsula |
Project ID: | 0001599 |
May 05, 2022 01:28 PM AKDT
Addendum No. 3: Changes completion date and specifications.
May 03, 2022 03:27 PM AKDT
Addendum No. 2: Changes bid opening date.
May 03, 2022 01:00 PM AKDT
Notice to Bidders No. 01: Provides call-in information to allow interested parties to attend bid opening remotely.
May 02, 2022 11:27 AM AKDT
Addendum No. 1: Provides question/answer and makes changes to multiple plan sheets.
April 08, 2022 11:30 AM AKDT
Homer: West Hill Road Pavement Preservation Plan Holders List
Contract#: CFHWY00300
Federal# / IRIS Program#: 0001599 / CFHWY00300
Region: Central Region
Bid Opening Date: 05/04/2022
Advertise Date: 04/08/2022
Description: This federally funded project will resurface the West Hill Road from the Sterling Highway to Skyline Drive. Project work includes drainage, signing, striping, dig-outs, curb ramps, guardrail, and paving.
On the Job Trainees/Apprentices (item 645): 0 Trainee(s), 0 Hours
Engineer's Estimate Range: Between $2,500,000 and $5,000,000