Questions for Proposal Z675170000

Header information table
Letting ID: Z000067517_1 Call Order: 1
Questions for this proposal
Subject Number Asked Answered
(76 Questions)
Quantity Calcs - Please provide the Quantity Calculations for this project - ASAP. 1 06/02/2020 06:50 AM 06/03/2020 10:12 AM
ITEM P-315 - Emulsified Asphalt Cement AASHTO M 140 is not the correct Specification. Use Emulsi... 2 06/02/2020 02:13 PM 06/17/2020 05:54 PM
Item D701.040.0018 - Item D701.040.0018 CAA Pipe, 18-inch in the bid tab, does not exist in specific... 3 06/09/2020 10:46 AM 06/17/2020 05:54 PM
Item D701.040.0024 - Item D701.040.0024 CAA Pipe, 24-inch in the bid tab, does not exist in specific... 4 06/09/2020 10:50 AM 06/17/2020 05:55 PM
Item G130.140.0000 - Item G130.140.0000 Radios is noted as ‘per each’ at end of the Basis of Payment... 5 06/09/2020 10:51 AM 06/19/2020 02:37 PM
Item L125.030.0000 - Item L125.030.0000 Medium Intensity Runway Edge Light, L-861 in the specificati... 6 06/09/2020 10:52 AM 06/17/2020 05:56 PM
Cross Sections - Are there any cross sections for the project that you can make available? 7 06/09/2020 10:53 AM 06/19/2020 02:38 PM
Item L125.035.0000 - Is Item L125.035.0000 Medium Intensity Taxiway Edge Light, L-861T in the spec s... 8 06/09/2020 10:54 AM 06/17/2020 05:56 PM
Item L125.060.0000 - Item L125.060.0000 Primary Handhole, L-868, Size B in the bid tab is listed as ... 9 06/09/2020 10:55 AM 06/17/2020 05:57 PM
Item L125.110.0000 - Item L125.110.0000 Relocate Existing Airport Sign, Type L-858/Remove in the bid... 10 06/09/2020 10:56 AM 06/17/2020 05:57 PM
Item L125.130.0000 - Item L125.130.0000 Airport Sign, L-858 in the bid tab is listed as Item L125.13... 11 06/09/2020 10:57 AM 06/17/2020 05:58 PM
Item L125.180.0000 - Item L125.180.0000 Temporary Runway Lighting System in the bid tab, does not ex... 12 06/09/2020 10:58 AM 06/17/2020 05:58 PM
Item L125.450.0000 - Item L125.450.0000 Remove Airport Electrical/Relocate in the bid tab is listed ... 13 06/09/2020 11:00 AM 06/17/2020 05:58 PM
Item P209.080.000 - Item P209.080.000 Crushed Aggregate Base Course is listed by the CY. Would the D... 14 06/09/2020 11:01 AM 06/19/2020 02:38 PM
Item P315.010 - Item P315.010 Emulsified Asphalt treated base is listed for payment by the “ton” on ... 15 06/09/2020 11:03 AM 06/17/2020 06:01 PM
Item P620.060.0000 - Item P620.060.0000 Painted Marking Removal in the bid tab, does not exist in sp... 16 06/09/2020 02:07 PM 06/17/2020 06:02 PM
Item P620.070.0000 - Item P620.070.0000 Temporary Runway and Taxiway Painting in the bid tab, does n... 17 06/09/2020 02:08 PM 06/17/2020 06:02 PM
Item P641.030.0000 - Item P641.030.0000 Temporary Erosion, Sediment, and Pollution Control by the lu... 18 06/09/2020 02:09 PM 06/17/2020 06:02 PM
Sheet A11/12 - Sheet A11/12, it is unclear in which phase the blast pad typical section work is to b... 19 06/09/2020 02:10 PM 06/19/2020 02:39 PM
Sheet A11 - Sheet A11 Note 3 states TW A & B to be open at all times yet shows them with “X” closure... 20 06/09/2020 02:12 PM 06/17/2020 06:03 PM
Sheet A12 - Sheet A12 Note 3 states TW A & B to be open at all times yet shows them with “X” closure... 21 06/09/2020 02:14 PM 06/19/2020 02:39 PM
Sheet A13 - A13 it is unclear where the boundary on the GA apron between the Phase 6 & 7 work is loc... 22 06/09/2020 02:15 PM 06/17/2020 06:04 PM
B Sheets - The B sheets use the terms ‘Reclaim’, ‘Recycle’, ‘Cold Planing’, Item P-161, & Item P-315... 23 06/09/2020 02:16 PM 06/19/2020 02:40 PM
Sheet B2 - Sheet B2 Legend has two bullet 6 and Detail 5/B2 has a bullet 7 that cannot be found on t... 24 06/09/2020 02:18 PM 06/19/2020 02:40 PM
Sheet B3 - Sheet B3 Detail 6, bullet 4 is for 6” crushed agg base course. The title of the detail is... 25 06/09/2020 02:20 PM 06/19/2020 02:41 PM
Sheet B4 - Sheet B4 detail 3 & 4 shows a 20 to 1 wedge of material on the shoulder. What is that mat... 26 06/09/2020 02:22 PM 06/19/2020 02:41 PM
Sheet B5 - Sheet B5 Detail 3/B5 it titled ‘reclaim and Pave’. Please confirm the bid item bullet 3 i... 27 06/09/2020 02:23 PM 06/19/2020 02:42 PM
Sheet C1 - Sheet C1 The Basis of Estimate table includes Item P610.060.0000 Reinforced Concrete Hard... 28 06/09/2020 02:24 PM 06/17/2020 06:05 PM
Sheet E1 - Sheet E1 please confirm that the specified product part numbers for the Aircraft Tie Down... 29 06/09/2020 02:25 PM 06/17/2020 06:05 PM
F Sheets proposed phase boundary - Is it possible to get the proposed phase boundary’s illustrated o... 30 06/09/2020 02:26 PM 06/19/2020 02:42 PM
F Sheet - typical sections - The Legends on the F sheets do not correlate very well with the typical... 31 06/09/2020 02:27 PM 06/17/2020 06:06 PM
Sheet F3 - Sheet F3 TW A and TW B both refer to detail 4/E2. There is no detail 4 on sheet E2. Pleas... 32 06/09/2020 02:28 PM 06/17/2020 06:07 PM
Sheet F4 - Sheet F4 shows detail 3/B2 and 4/B2 on RW 2/20. Those details are for the Heavy Aircraft ... 33 06/09/2020 02:29 PM 06/17/2020 06:07 PM
Sheet F6 - Sheet F6 hardstand at ‘L’ 8+16, 204LT has leader notes indicating it is Hardstand ‘C’ and... 34 06/09/2020 02:31 PM 06/17/2020 06:08 PM
Sheet F7 - Sheet F7 the tie downs located between TW C and TW D do not have a typical section callou... 35 06/09/2020 02:32 PM 06/19/2020 02:43 PM
Sheet F8 - Sheet F8 has a hatched area of Mill 3”/HMA 3” that is also cut by section 4/B3. Detail 4/... 36 06/09/2020 02:32 PM 06/17/2020 06:08 PM
State Ferry Dock Facility - Will the State Ferry Dock facility be available for contractor barge use... 37 06/09/2020 02:33 PM 06/19/2020 02:43 PM
Section P152-3.1 - Section P152-3.1 indicates to dispose of unsuitable material in waste areas shown... 38 06/09/2020 02:34 PM 06/19/2020 02:43 PM
Section P209 - Section P209 first two paragraphs on page two defines RAM. Will the RAM material be a... 39 06/09/2020 02:35 PM 06/17/2020 06:09 PM
Section P209 - Section P209 Linear Grading paragraph incorrectly identifies Section P161 as ‘Reclaim... 40 06/09/2020 02:36 PM 06/17/2020 06:09 PM
Section P-315 - Section P-315 specifies HFMS-2S for the emulsified asphalt cement. Will the Departme... 41 06/09/2020 02:37 PM 06/17/2020 06:10 PM
Section P401 - Section P401-4.2 lists the HMA plant capacity minimum as both 250 TN/Hr and 400 TN/Hr... 42 06/09/2020 02:38 PM 06/17/2020 06:11 PM
Section P501 - For section P501, where is the 94cy of concrete pavement work? And can the acceptance... 43 06/09/2020 02:39 PM 06/17/2020 06:11 PM
Section P650 - Section P650 Basis of Payment states “At contract price, per set, for the pay item…” ... 44 06/09/2020 02:40 PM 06/17/2020 06:12 PM
Section T901-5.01 - Section T901-5.01 states mulching will be measured and paid for under Item T-908... 45 06/09/2020 02:41 PM 06/17/2020 06:12 PM
Staging/Stockpile Area - How is the Staging / Stockpile area (~20 acres) get paid for Clearing and G... 46 06/09/2020 02:43 PM 06/17/2020 06:13 PM
Item P315.010 - Item P315.010 Emulsified Asphalt treated base is listed for payment by the “ton” on... 47 06/09/2020 02:44 PM 06/17/2020 06:13 PM
Item P209.080.000 - Would the department consider changing Item P209.080.000 Crushed Aggregate Base ... 48 06/09/2020 02:45 PM 06/17/2020 06:13 PM
State Ferry Dock - Will the contractor be able to use State Ferry Dock for barges 49 06/09/2020 02:46 PM 06/19/2020 02:44 PM
Section 401-4.2 - Section 401-4.2 Asphalt mixing plant list a 250 tons per hour plant and a 400 tons... 50 06/09/2020 02:46 PM 06/17/2020 06:14 PM
401-6.2.f.(4) (b) - Would the department consider removing The Profilograph smoothness section of th... 51 06/09/2020 02:47 PM 06/19/2020 02:45 PM
Sheet F3, Note 5 - Sheet F3, Note 5: TRANSITION FROM "F" STA. 21+00 TO 21+44.1, TRANSITION SLOPE TO ... 52 06/09/2020 02:49 PM 06/19/2020 02:46 PM
Air Taxi Apron - AIR TAXI APRON "T" STA. 10+00 OFF= 0.00 N: 48924.8453 E: 38856.8962 SEE SHEET ... 53 06/09/2020 02:50 PM 06/19/2020 02:46 PM
Sheet B2 Detail Typical 1 - Sheet B2 Detail Typical 1 – Heavy Aircraft Apron, Sheet B5 Detail 1 Typi... 54 06/09/2020 02:52 PM 06/19/2020 02:46 PM
Temp Lighting - Can the department provide more scope and detail for the temporary lighting? There ... 55 06/10/2020 11:09 AM 06/19/2020 02:47 PM
Phasing Stationing - It doesn't appear that the stationing shown in Phase 4 and Phase 5 of "O" 60+21... 56 06/10/2020 01:14 PM 06/19/2020 02:47 PM
Phase 4 - The first Phase 4 work area shown in the Legend on Sheet A12 calls for 4" Hot Mix Asphalt;... 57 06/10/2020 01:26 PM 06/19/2020 02:48 PM
Phase 4 Blastr Pad work - I wanted to clarify a question I asked earlier with regards to the Legend ... 58 06/10/2020 01:38 PM 06/19/2020 02:48 PM
General Aviation Apron Sections - Details 3/B3 and 4/B3 refer to structural section 6/B3. 6/B3 refe... 59 06/11/2020 09:12 AM 06/19/2020 02:49 PM
Structural Section for R/W 2/20 Blast Pads - Typical Section 6/B4 shows a call out for 7 however the... 60 06/12/2020 05:59 AM 06/19/2020 02:49 PM
Structural Sections Plan Sheet B2 - Structural Section 5/B2 on Sheet B2 is labeled as Cold Plane & P... 61 06/12/2020 08:38 AM 06/19/2020 02:49 PM
401-4.14 Joint Heater - If a infrared joint heater is utilized, will this eliminate the use of joint... 62 06/16/2020 11:09 AM 06/19/2020 02:50 PM
P401.010 HMA bid quantity - It appears the quantity is based on paving 2 inch on runway 11/29 while ... 63 06/16/2020 11:13 AM 06/19/2020 02:50 PM
P151.040 Clear and grub - Will the indicated staging areas for stockpiles be paid for under this ite... 64 06/16/2020 11:16 AM 06/19/2020 02:50 PM
Phasing Schedule - Are there any calendar completion days associated with any of the phases or does ... 65 06/16/2020 11:21 AM 06/19/2020 02:51 PM
P401-4.14 - If an infrared joint heater is used does this eliminate the application of joint adhesiv... 66 06/16/2020 03:47 PM 06/17/2020 08:25 AM
P401 - The HMA bid quantity appears to be based on 2 inches on runway 11/29 while the typical shows ... 67 06/16/2020 03:48 PM 06/17/2020 08:26 AM
Completion - Are there any calendar days associated with completing individual phases or does the fi... 68 06/16/2020 03:48 PM 06/17/2020 08:26 AM
P151 - Will the contractor be paid clear and grub for designated stockpiling area? 69 06/16/2020 03:49 PM 06/17/2020 08:26 AM
P207.130 - The reference to AASHTO M 140 contains specifications for 15 grades of emulsified asphalt... 70 06/16/2020 03:50 PM 06/19/2020 02:51 PM
Aggregates - Our firm is looking at the noted solicitation which involves, among other things a subs... 71 06/17/2020 10:54 AM 06/22/2020 12:21 PM
Gustavus Airport Apron R/W, T/W - Asphalt Plant Capacity - Will a 350 ton per hour asphalt plant, wi... 72 06/18/2020 03:08 PM 06/22/2020 12:21 PM
D701-Drainage - Can you tell us what gauge of aluminum culvert is needed on the project? Usually it... 73 06/19/2020 10:29 AM 06/22/2020 12:22 PM
P-501 - Item P-501: the concrete specifications for this project are geared more towards slip-form... 74 06/20/2020 10:33 AM 06/22/2020 12:22 PM
P-501 - With no concrete batch plant available in Gustavus will it be acceptable to batch with bulk ... 75 06/22/2020 08:56 AM 06/23/2020 07:07 AM
Gustavus Ferry Use - Please see Notice To Bidders 1, Page 2, Facility Use Of Limitations, Second Sen... 76 06/24/2020 10:36 AM 06/24/2020 02:57 PM

Error

Bid Express: New Roads

Bid Express: New Roads is a series of updates aimed at creating a more personalized experience that better caters to individual needs, jobs, and responsibilities.

Over the coming months, we'll be rolling out redesigned experiences to you across the entire service. Learn more.

Don't worry, if you don't love it, you can switch back to classic Bid Express for a limited time while you get used to the new look.

No thanks