Question asked regarding 20211109006

Header information table
Letting ID: 20211109 Call Order: 006
Number: 3

Removal/Traffic Control

For the traveling public safety, given the integrity of the prestress girder and its stability when the deck is removed, would WI DOT detour IH-90/94 EB for 6 to 8 hours during the removal of the deck and girder.

Asked at 10/19/2021 01:45:10 PM


IH 90/94 will not be detoured. The traffic control plan is to utilize lane closures to do the overhead work and then use a rolling stop to remove the girder. It is a similar scenario for placing the new girder as well.

Answered at 10/20/2021 11:41:13 AM

Error

Bid Express: New Roads

Bid Express: New Roads is a series of updates aimed at creating a more personalized experience that better caters to individual needs, jobs, and responsibilities.

Over the coming months, we'll be rolling out redesigned experiences to you across the entire service. Learn more.

Don't worry, if you don't love it, you can switch back to classic Bid Express for a limited time while you get used to the new look.

No thanks